The project is for the design and completion of four blocks of office units, together with the completion of the external works and provision of new incoming services.
The project is on schedule and due for completion in August 2018.
Durham Gate (North) Investment Co Ltd
Durham Gate, Spennymoor
Commercial
Employers Agent, Quantity Surveyor and Principal Designer
Padgett White Architects Ltd
Meldrum Construction
£3.2m
30 Weeks
JCT Design & Build Contract 2011
2,163m2